The utility clearance rules are widening. Can we build the capacity to deliver?

Oct 28
11 min read

Changes to New Zealand’s tree-clearance requirements are bringing the capacity of utility vegetation programmes into focus. Networks need to understand what additional work will be required, while contractors need to decide what people, equipment and training they can commit to delivering it.


The immediate question sounds straightforward: Will there be enough utility arborists? Answering it requires more than counting workers or vacancies, because an employer can have people available but lack the experience, authorisations or supervision needed to form another productive crew. A network can identify substantial vegetation risk without having the permissions, funding and prepared work needed to put that crew to work.

What is changing?

The amendments to the Electricity (Hazards from Trees) Regulations 2003 address three different sources of vegetation exposure: Branches growing above conductors, unsuitable future planting, and trees that could fall onto lines. Each has different implications for field production, assessment and landowner engagement.

17 October 2026 — the clear-to-the-sky transition ends. The extended Growth Limit Zone prevents branches overhanging affected conductors within the zone’s horizontal boundaries, even where they sit well above the conventional clearance envelope. It applies to uninsulated lines above 11 kV, conductors with spans exceeding 150 metres, and uninsulated lines of 11 kV or below outside urban areas. Short-span insulated conductors, including aerial-bundled conductors, and short-span urban lines of 11 kV or below retain the surrounding clearance envelope. Trees protected under district plans are exempt from the vertical extension, although ordinary clearance requirements still apply. The transition’s end brings the additional overhead space within the normal Cut or Trim Notice obligations; it is not a deadline by which every affected tree must already have been cut. [1]

23 July 2027 — low-height planting requirements apply. On unforested land outside urban areas, the low-height planting zone extends 24 metres horizontally from the conductor’s vertical plane. Planting generally requires reasonable grounds to believe that the mature tree will be shorter than its horizontal fall distance to the conductor. Exceptions include shelter belts and land administered under specified conservation legislation. These provisions principally address future exposure rather than requiring immediate clearance of existing trees. [2]

23 July 2028 — Treefall Hazard Notices become available. Works owners can issue notices requiring removal of qualifying trees assessed as moderate or high hazards within the Treefall Hazard Zone, which extends horizontally up to 24 metres beyond the Growth Limit Zone. The usual removal periods following receipt of a notice are 45 working days for moderate hazards and 25 for high hazards, subject to the regulations’ dispute provisions. Statutory assessments can already be undertaken, but the transition restricts issuing notices, allowing networks to begin assessment and programme preparation beforehand. [3]

The regulations require written advice from a “suitably qualified and experienced arborist”, but leave the qualification and experience threshold undefined. They do not prescribe TRAQ, QTRA or another named tree-risk qualification or system. Instead, Schedule 3 specifies the assessment framework, covering both the likelihood of a tree falling and its potential impact on electricity supply and public safety, with the works owner responsible for the resulting hazard classification. [4]

For workforce planning, the practical question is how networks will establish and document the competence required to provide that advice, and what additional development experienced utility arborists may need. Clearance experience may provide a useful foundation, but assessing and explaining tree-failure likelihood requires consideration in its own right.

Some programmes may already maintain comparable clearances, while others may face substantial additional work. The workforce implications will depend on existing practices, equipment, work preparation and how networks commission delivery, so the changes do not translate directly into a particular increase in headcount.

What the disclosures reveal

Electricity distribution businesses publish detailed information disclosures under Commerce Commission requirements. Their vegetation expenditure and reliability schedules provide a starting point for understanding the scale of existing programmes and the problems those programmes are intended to address.

Powerco’s FY26 disclosure records approximately $12.5 million in vegetation-management expenditure, while Northpower records approximately $3.4 million. Both figures include assessment and other vegetation activities alongside felling and trimming, and exclude separately recorded vegetation-related emergency expenditure. These are examples of substantial continuing programmes, rather than estimates of labour costs or the national market. [5, 6]

Reliability reporting also shows why statutory clearance and interruption risk are not the same problem. Orion reported that 18.0 of its 18.4 vegetation-coded interruption minutes per customer came from out-of-zone vegetation in FY26, approximately 98% of its vegetation-coded interruption duration, not 98% of all outages. This is one network’s reported classification, rather than an independently established account of every fault’s cause, and should not be generalised to other networks. [7]

The figure does not demonstrate that routine in-zone clearance is misplaced, since successful preventive work may help explain the relatively small in-zone contribution. It does illustrate why vegetation programmes extend beyond maintaining the clearance envelope, with wider risks requiring assessment, landowner engagement and decisions about which work to commission.

The disclosures establish expenditure and reported exposure more clearly than they establish workforce needs. They cannot, on their own, tell us whether delivery is constrained by crew numbers, assessment capability, access, funding or the organisation of work.

From identified risk to work a crew can perform

An identified risk is not yet a prepared job, as Northpower’s disclosed process illustrates. Specialist inspectors assess vegetation, estimate the resources required and prepare work packs before clearance is allocated according to risk and available resources. This makes the distinction between identifying work, preparing it and delivering it explicit. [6]

An identified risk is not yet a prepared job.

This distinction is important to recognise when interpreting a shortage. If prepared, funded work repeatedly waits because no suitable crew is available, production capacity is a plausible constraint. If crews are waiting for permissions, scoping or access, adding workers alone may do little to increase output, and both constraints can occur within the same programme.

Someone also has to prioritise work, allocate it and check its performance. Where those responsibilities sit is an organisational choice, and public documents describe several arrangements across New Zealand networks.

Vector’s 2024 Asset Management Plan describes separating inspection and administration from physical delivery. An independent consultancy undertakes the inspection and administration component, which includes assessment and prioritisation of work packs, while vegetation service providers carry out the cutting. [8]

Orion described a different model to the Commerce Commission in 2023. Its staff scope high-voltage maintenance by driving feeder lines, group the work into substation contract areas and tender the trimming externally, while also identifying higher-risk out-of-zone trees and dealing with affected owners. [9]

MainPower’s 2025 Asset Management Plan describes a greater role for internal production. Two full-time arborist crews carry out most vegetation maintenance and supervise third-party contractors working near its lines, with contractors increasingly supplementing delivery. [10]

These arrangements distribute planning knowledge, supervision and accountability differently between networks and suppliers. They also create different demands for internal capability, since buying physical clearance work does not remove the need to understand and manage the programme around it.

The importance of oversight has a documented example in the 2019 High Court case concerning Vector’s breaches of regulated network quality standards. The agreed facts identified insufficient strategic direction, oversight, auditing and incentives in vegetation-provider arrangements, alongside wider weaknesses in the allocation of field-service responsibilities. The case concerned several network-management failures, not vegetation alone, but demonstrates why the allocation of responsibility deserves attention alongside the resources available to carry out work. [11]

Who carries the cost of coordination?

A network dealing with one or two substantial contractors can leave many scheduling, workforce and reporting responsibilities inside those firms. If the same physical work is divided among numerous small providers, those functions remain necessary, and some combination of the network, an intermediary or another programme manager has to perform them.

This does not mean small contractors are inherently inefficient or incapable, because physical production and programme coordination are different contributions. A small firm may be well equipped to complete particular jobs while lacking the administrative capacity, geographic coverage or reserve resources expected of a programme contractor.


The trade-off is visible outside electricity too. Auckland Council describes its 2017 maintenance model as consolidating work into fewer large contracts to simplify delivery and manage risk, while its replacement process seeks a mix of large and smaller suppliers and greater internal expertise. This illustrates the continuing need to balance the convenience of fewer supplier relationships with the security of a broader range of providers. [12]

For utility vegetation programmes, the useful question is what functions the buyer expects a contractor to carry and where those functions can be organised effectively. Creating opportunities for smaller suppliers requires decisions about who will prepare their work, coordinate their contribution and assure its quality, as well as whether they can physically perform the cutting.


What happens to capability when contracts move?

Networks need vegetation management over the long term, but an individual contractor’s commitment of work is bounded by its agreement. A continuing need for clearance therefore does not necessarily give the employer funding a worker’s development an equally long period in which to recover that investment. Published network plans illustrate this distinction between long-term programme forecasts and shorter supplier agreements. [13]


A continuing need for clearance therefore does not necessarily give the employer funding a worker’s development an equally long period in which to recover that investment.

A contractor considering a trainee commits more than course fees, because development also uses experienced workers’ time and can reduce immediate crew output. The prospect of retaining sufficient work long enough to benefit from that investment therefore matters, alongside training costs and the contribution the learner can make while developing. The calculation may also change as a contract approaches renewal, particularly if there are few opportunities to deploy the worker elsewhere.

Where experienced workers follow a programme to an incoming employer, local capability may remain available to the network while the employer that developed it loses the opportunity to benefit from its investment. An incoming employer may offer better development, however, and contractors with other programmes may be able to retain and redeploy staff. The practical question is whether contract duration, renewal expectations and alternative work give employers enough confidence to invest in developing people, even though the underlying demand for their skills continues.

Developing another utility arborist

Recruitment is one response to a capacity constraint, but employing an experienced arborist does not automatically make that person ready for every utility task. Arboricultural skill must be combined with the electrical-hazard competence, supervision and permissions required for the particular work.

An employer can have people available but lack the experience, authorisations or supervision needed to form another productive crew.

The Approved Code of Practice for tree maintenance around power lines distinguishes between the competent worker zone and the close working zone. Clause 8.1.4 specifies at least one competent worker on site in the former, with trainees and non-competent workers under direct supervision, while clause 9.6 specifies at least two competent workers throughout close working. These provisions describe competence rather than a universal NZQA-level staffing rule; WorkSafe also cautions that the code predates current health-and-safety legislation and must be read alongside applicable current requirements. [14]

An experienced utility arborist can therefore contribute both to production and to the supervision needed to develop another worker. Adding beginners may initially increase demands on the very people whose capability the employer needs to reproduce, particularly where the available competent workers already limit the number of crews that can operate independently.

NZQA standards help distinguish knowledge from practical competence. Unit standard 28493, at Level 3, addresses knowledge of vegetation and tree work near power lines and cables, while unit standard 28494, at Level 4, covers practical work and utility-arboriculture emergency procedures. The latter requires the former or equivalent knowledge and skills, and three practical observations across different workplace activities, with one permitted to be simulated. These are individual standards rather than complete qualifications, but they illustrate why theory, supervised experience and assessment all need provision. [15, 16]

Access to that development has been an issue for smaller employers. In my 2021 research into skill mismatches and worker shortages in New Zealand arboriculture, a Wellington manager described sending workers to other cities for powerline training or paying to host training himself. He regarded the difficulty of obtaining and maintaining network approval as a barrier to entering larger utility contracts, an account that identifies a historical access problem without establishing the availability of training today. [17]

Recruiting an already competent utility arborist can meet an individual employer’s immediate need, but moving an existing worker between firms does not itself increase the available workforce. Developing additional capability requires supervised work, assessment and a viable allocation of the costs involved. For workforce planning, the distinction is important as  an individual employer can fill a vacancy without the wider system gaining another trained worker. 

Technology and the work ahead

Workforce planning also needs to account for changes in how work is identified and performed. Powerco reports using satellite imagery to identify high-risk vegetation sites, with its categories still being refined, illustrating how improved information can reveal work as well as support its prioritisation. A newly recorded site is not necessarily a new physical hazard or a discrete cutting job. [5]

Mechanisation, work preparation and assessment can each alter the labour required for delivery. Equipment can reduce climbing or manual handling on suitable jobs, prepared work can reduce waiting, and more precise assessment can change which trees receive attention. The resulting workforce requirement depends on the mix of tasks and methods, rather than simply the number of trees identified.

Essential work also competes for funding, as Unison’s FY26 disclosure illustrates. It reports deferring some non-traditional vegetation activities to offset higher corrective-maintenance expenditure, demonstrating a programme trade-off rather than evidence that a shortage of workers caused the deferral. [18]

For employers and networks, the central question is therefore: What work is not being delivered, and what is preventing it from becoming completed work? Where authorised crew capacity is the constraint, training, retention and supervision deserve attention; where work is held up by assessment, permissions or preparation, recruiting more cutters may achieve very little.

The amendments make this inquiry timely, while the existing programmes show why the answer must extend beyond vacancies. Building capacity requires a reliable flow of prepared work, clear responsibility for delivery and enough experienced people to develop others, supported by commercial arrangements that make the investment worthwhile. Those are decisions employers and networks can examine now, even before the full scale of the additional work becomes clear.


References

  1. Electricity (Hazards from Trees) Regulations 2003, version as at 23 July 2026. Clear-to-the-sky requirements and transition: Schedule 2, clauses 1–3; Schedule 1, clauses 3–4 and 11; regulation 8. Consolidated PDF pp. 41–45 and 47–49.

  2. Electricity (Hazards from Trees) Regulations 2003, version as at 23 July 2026. Low-height planting requirements: Regulation 4, definition of low-height planting zone; regulation 11J, consolidated PDF pp. 20–21.

  3. Electricity (Hazards from Trees) Regulations 2003, version as at 23 July 2026. Treefall Hazard Notices and transition: Regulation 4, definition of treefall hazard zone; regulations 11A–11D; Schedule 1, clause 15, consolidated PDF p. 46.

  4. Electricity (Hazards from Trees) Regulations 2003, version as at 23 July 2026. Treefall-hazard assessment: Schedule 3, clauses 3–5, particularly clause 3(2)(a), consolidated PDF pp. 50–52.

  5. Powerco Limited. Electricity information disclosure, year ended 31 March 2026. Schedule 6b(i), PDF p. 27: Vegetation management $12.513m, with $0.411m vegetation-related emergency expenditure recorded separately; PDF p. 77: Satellite identification and evolving risk categories.

  6. Northpower Limited. Information Disclosure Requirements, DY26. Schedule 6b(i), PDF p. 21: Vegetation management $3.362m, with $0.488m vegetation-related emergency expenditure recorded separately; PDF p. 68: Assessment, work preparation and resource allocation.

  7. Orion New Zealand Limited. FY26 information disclosures. Schedule 10(ii), PDF p. 34: Vegetation-coded SAIDI and its out-of-zone component.

  8. Vector Limited. Electricity Asset Management Plan 2024–2034, section 8.8.1: Allocation of inspection, administration and physical vegetation work.

  9. Commerce Commission. EDB and Field Service Provider Meeting Notes — Orion, 15 November 2023, PDF pp. 1–2: In-house scoping, tendered trimming and out-of-zone work.

  10. MainPower New Zealand Limited. Asset Management Plan 2025–2035, section 7.7.1: In-house arborist crews and supplementary contractors.

  11. Commerce Commission v Vector Limited [2019] NZHC 540, 22 March 2019. Judgment, paragraphs 18–19, particularly 19(d)(v) and 19(e)(iii), PDF pp. 9–10.

  12. Auckland Council. “Significant maintenance contracts up for renewal”, 25 February 2026.

  13. Aurora Energy Limited. Information disclosures for the year ending 31 March 2026, PDF pp. 80 and 87: Agreement terms and nominal ten-year vegetation programme.

  14. WorkSafe New Zealand. Approved Code of Practice for Safety and Health in Tree Work, Part 2: Maintenance of Trees Around Power Lines, clauses 8.1.4 and 9.6, PDF pp. 50 and 58. See also WorkSafe’s accompanying guidance on the code’s status alongside current legislation and standards.

  15. NZQA. Unit standard 28493, version 3, Level 3: Knowledge of vegetation and tree work near power lines and cables.

  16. NZQA. Unit standard 28494, version 4, Level 4: Practical vegetation work near power lines and utility-arboriculture emergency procedures; entry information and assessment conditions.

  17. Isaacs, J. (2021). Skill mismatches and worker shortages in the New Zealand arboriculture industry. Master of Business Studies thesis, Massey University, pp. 105–106.

  18. Unison Networks Limited. Information disclosures 2026, PDF p. 78: Deferral of non-traditional vegetation activities.


About the author

James Isaacs is an arboricultural workforce strategist at Ostix Consulting. His Master of Business Studies research examined skill mismatches and worker shortages in New Zealand arboriculture. His work draws on experience as an arboriculture business owner, field arborist and organisational improvement practitioner.